Nov 23, 2026 · Langley · Langley Advance Times

Industrial Avenue and 203 Street will see another partial closure on Nov. 24 as work continues on the Surrey Langley SkyTrain extension. The closure runs from 6 a.m. to 8 p.m.; construction starts at 7 a.m., with lane and traffic-direction changes nearby.

YoLink AI 资料配图

Industrial Avenue at 203 Street in Langley will be partially closed again as construction continues on the Surrey Langley SkyTrain extension. The closure is scheduled for Tuesday, Nov. 24, from 6 a.m. to 8 p.m., although construction will begin at 7 a.m. Crews will pour concrete and install track on part of the elevated guideway already in place at the east end of Industrial Avenue.

Traffic changes are as follows: Industrial Avenue will remain eastbound only on its western section, from 200 Street to 201A Street; 201A Street will be southbound only from Industrial Avenue to Fraser Highway; traffic on Industrial Avenue east of 201A Street will alternate, with one lane open; and drivers will not be able to access 203 Street from Industrial Avenue.

The Surrey Langley SkyTrain Project announced the changes and asked drivers in the area to follow traffic-control personnel and road signs. Industrial Avenue and the area around 203 Street have seen multiple closures. The street is one of the line’s major construction sites.

Langley City Centre, the extension’s easternmost station, is being built on the east side of 203 Street. Large gantry cranes are constructing most of the elevated guideway. Because space between existing buildings is tight near the station, the final few guideway segments were cast as complete spans and lifted into place using conventional cranes. Construction at the future station site began two years ago, and work on the pylons has been underway for some time.

The pylons are nearly complete. The Langley Launcher gantry, which assembles the guideway, arrived in Langley earlier this year and is now moving east from the Willowbrook Station site. It is less than 1.5 kilometres from the end of the line.

Most of the guideway is expected to be in place by late this year or early next year, as the four gantries finish their work. The project still has to complete eight stations and power-supply structures, and lay track along the entire route. SkyTrain cars will then be tested on the new route before it opens to passengers. The project is expected to open in late 2029.

Read the original source · Langley Advance Times

GOOD THINGS HAPPEN HERE

Download Yo! Vancouver

Scan with your phone camera to discover more local favourites.

Scan to download Yo! Vancouver

Or choose your app store

Download on the App StoreGet it on Google Play