B.C. exempts FortisBC Tilbury LNG expansion from utility approval step
British Columbia has exempted FortisBC’s proposed $2-billion Tilbury LNG expansion from one utility approval, while other permits and regulatory approvals will still be required.

The British Columbia government has issued an order exempting FortisBC from one regulatory step for its proposed $2-billion expansion of the Tilbury liquefied natural gas facility in Delta.
Normally, a developer must obtain a certificate of public convenience and necessity from the B.C. Utilities Commission before building or expanding a public utility plant or system. Energy Minister Adrian Dix said bypassing that requirement will shorten the process, though the project still needs all other applicable permits and approvals.
The province says construction could begin by the middle of next year, with operations beginning as early as 2031. It estimates the project will create 1,100 construction jobs and generate $260 million in tax revenue.
The Tilbury site has operated as a natural-gas storage facility since 1971. It now produces LNG for vessels and is working with the Vancouver Port Authority on marine fuelling service. FortisBC says the facility already supplies Seaspan Ferries and BC Ferries.
A separate proposal, Tilbury Phase 2, remains in B.C.’s environmental assessment process. Public comments are open until July 27, 2026, and the province anticipates a decision later that year.